New Orleans International Airport West Terminal Utilities

Burk-Kleinpeter, Inc. (BKI) was contracted by the New Orleans Aviation Board to provide design and construction administration for a new fire protection system and primary power distribution system serving the New Orleans International Airport.

The project included construction of a new emergency water supply well, a new utilities building to house emergency fire pumps and emergency generators as well as the control systems to operate all emergency water and power supplies serving the main terminal building. It also included a 400,000-gallon ground-level water-storage tank and complete new 16" water distribution loop for fire-protection supply lines around the terminal and new primary electrical power conduits from the utility building to the terminal.

Construction cost was approximately $4.5 million.