Burk-Kleinpeter,
Inc. (BKI) was contracted by the Regional
Transit Authority to provide construction
management for a $25 million bus
maintenance facility and three-story
parking garage.
To prepare the site, BKI
oversaw the demolition of the 100-year-old
maintenance facility, including salvage of the
historical wood truss systems for later re-use. BKI
also administered extensive soil remediation for
hydrocarbon contamination.
The new facility includes a
three-story reinforced structure for ground-level
bus maintenance operations and second- and
third-floor administration offices and employee
parking. Additional structures include a bus vacuum
and wash down facility, money counting office,
perimeter security fencing and a security
guardhouse at the entrance to the
complex.
Construction management
services consisted of project scheduling with
Primavera software, review of shop drawings,
preparation of plan changes, review of invoices,
construction inspection, and project closeout
services.
Construction cost was
approximately $22 million.